Project:

Temporary ACOUSTIC wall in Crystal Hall

Client

DDLAR

Location

Baku, Azerbaijan

Client Requirement

Temporary ACOUSTIC wall for the Baku 2015 European Games to separate the BOXING from the VOLLEY BALL

Partition Solution used

F60S close jointed industrial finish painted black

Partition Dimensions

155m long by maximum height of 26m

Build Programme

DDLAR gave a completion deadline of 28th March 2015 which gave 22 days onsite

Project completion

PJS Solutions completed the project in 20 days onsite

Fire Resistance

One hour fire rating

Acoustic Rating

54 dB acoustic performance (Live test onsite) please email for test results

Robustness

Severe duty Rating

Notes

Even though the project was 3000 miles from our office we completed the project on time and have had extremely good reference from the client.